Estimated time: 3073:00 Estimated remaining time: 2994:18

# Project Tracker Status Priority Subject Assignee Updated Parent task Author Category Start date Due date Estimated time Estimated remaining time Total estimated time % Done Created Closed Last updated by
288 Daily Tasks Task New Normal Testing CTP functionality in development server Manoj Soni 02/03/2026 10:27 AM Kishan Nayak 01/30/2026 01/31/2026 8:00 8:00 8:00

02/03/2026 10:27 AM Actions
287 Daily Tasks Task New Normal Alignment and responsiveness issue fixed in pending document module Manoj Soni 02/03/2026 10:27 AM Kishan Nayak 01/30/2026 01/30/2026 0:00

02/03/2026 10:27 AM Actions
286 Daily Tasks Task New Normal Developed Marriage officer dashboard and stepper ui screen Manoj Soni 02/03/2026 10:27 AM Kishan Nayak 01/30/2026 01/30/2026 4:00 4:00 4:00

02/03/2026 10:27 AM Actions
285 Daily Tasks Task New Normal Resoved issues in pending document and incorporate changes as suggested by client Manoj Soni 02/03/2026 10:26 AM Kishan Nayak 01/30/2026 01/30/2026 0:00

02/03/2026 10:26 AM Actions
284 Daily Tasks Task New Normal Understand requirements of the Stamp Duty Payment module. Akashi Rai 02/03/2026 10:25 AM Kishan Nayak 01/30/2026 01/30/2026 4:00 4:00 4:00

02/03/2026 10:25 AM Actions
283 Daily Tasks Task New Low Meet internal teams to explain the Stamp Stock and Refund E-stamping process end-to-end. Akashi Rai 02/03/2026 10:25 AM Kishan Nayak 01/30/2026 01/30/2026 4:00 4:00 4:00

02/03/2026 10:25 AM Actions
282 Daily Tasks Task New Normal Design citizen-side screens for the Stamp Stock module, covering request and status. Akashi Rai 02/03/2026 10:25 AM Kishan Nayak 01/30/2026 01/30/2026 4:00 4:00 4:00

02/03/2026 10:25 AM Actions
281 Daily Tasks Task New Normal Updated the HLD (High-Level Design) and LLD (Low-Level Design) documents for the Refund Module. Kishan Nayak 02/03/2026 10:24 AM Kishan Nayak 01/30/2026 01/30/2026 0:00

02/03/2026 10:24 AM Actions
280 Daily Tasks Task New Normal Reviewed the Refund Module frontend development and provided suggestions for improvements. Kishan Nayak 02/03/2026 10:24 AM Kishan Nayak 01/30/2026 01/30/2026 0:00

02/03/2026 10:24 AM Actions
279 Daily Tasks Task New Normal Tested the UAT closer points of the Pending Document Module received during from the committee. Kishan Nayak 02/03/2026 10:20 AM Kishan Nayak 01/30/2026 01/30/2026 3:00 3:00 3:00

02/03/2026 10:20 AM Actions
278 Daily Tasks Task New Normal Marriage module form 16 save API Sachin Siddhpura 01/28/2026 10:42 AM Kishan Nayak 01/28/2026 01/29/2026 8:00 8:00 8:00

01/28/2026 10:42 AM Actions
277 Daily Tasks Task New Normal Resolved pending documents issue is any Sachin Siddhpura 01/28/2026 10:42 AM Kishan Nayak 01/28/2026 01/29/2026 8:00 8:00 8:00

01/28/2026 10:42 AM Actions
276 Daily Tasks Task New Normal Adhoc database changes and other requests Satendra Kumar 01/28/2026 10:41 AM Kishan Nayak 01/28/2026 01/29/2026 0:00

01/28/2026 10:41 AM Actions
275 Design Phase Task New Normal Working on HLD and LLD document for refunf module Satendra Kumar 01/28/2026 10:41 AM Kishan Nayak 01/28/2026 01/29/2026 8:00 8:00 8:00

01/28/2026 10:41 AM Actions
274 Daily Tasks Task New Normal Generate JWT generation implementation office wise hierarchy Amit Chauhan 01/28/2026 10:40 AM Kishan Nayak 01/28/2026 01/29/2026 8:00 8:00 8:00

01/28/2026 10:40 AM Actions
273 Daily Tasks Task New Normal Create UI pages for marriage module Manoj Soni 01/28/2026 10:39 AM Kishan Nayak 01/28/2026 01/29/2026 0:00

01/28/2026 10:39 AM Actions
272 Daily Tasks Task New Normal Fix issue in pending documents if any comes in during testing Manoj Soni 01/28/2026 10:38 AM Kishan Nayak 01/28/2026 01/29/2026 4:00 4:00 4:00

01/28/2026 10:38 AM Actions
271 Daily Tasks Task New Normal Start designing the stamp duty payment module Akashi Rai 01/28/2026 10:38 AM Kishan Nayak 01/28/2026 01/29/2026 0:00

01/28/2026 10:38 AM Actions
270 Daily Tasks Task New Normal Meet with stock management team to demonstarte the updated design and finalize it Akashi Rai 01/28/2026 10:37 AM Kishan Nayak 01/28/2026 01/28/2026 3:00 3:00 3:00

01/28/2026 10:37 AM Actions
269 Daily Tasks Task New Normal Update stock management design screens Akashi Rai 01/28/2026 10:36 AM Kishan Nayak 01/28/2026 01/29/2026 4:00 4:00 4:00

01/28/2026 10:36 AM Actions
268 Daily Tasks Task New Low Add design screens for the foreign bills and insurance flow Akashi Rai 01/27/2026 07:14 PM Kishan Nayak 01/27/2026 01/28/2026 4:00 4:00 4:00

01/27/2026 07:14 PM Actions
267 Daily Tasks Task New Normal Design the stamp stock prototype and update based on the feedback received to date Akashi Rai 01/27/2026 07:14 PM Kishan Nayak 01/27/2026 01/28/2026 4:00 4:00 4:00

01/27/2026 07:14 PM Actions
266 Daily Tasks Task New Low Met with internal team to explain the stamp stock process Akashi Rai 01/27/2026 07:13 PM Kishan Nayak 01/27/2026 01/27/2026 3:00 3:00 3:00

01/27/2026 07:13 PM Actions
265 Daily Tasks Task New Normal Met with Stamp stock team to demonstrate the design and finalize it Akashi Rai 01/27/2026 07:12 PM Kishan Nayak 01/27/2026 01/27/2026 3:00 3:00 3:00

01/27/2026 07:12 PM Actions
264 Daily Tasks Task New Normal Generate JWT for office Amit Chauhan 01/27/2026 07:11 PM Kishan Nayak 01/27/2026 01/28/2026 8:00 8:00 8:00

01/27/2026 07:11 PM Actions